STATUS OF WORK ON SELECTED HIGHWAY STRETCHES IN PUNJAB
April 23, 2008
The status of Chandigarh-Kiratpur, Amritsar-Pathankot and Jalandhar –Amritsar stretches are as under:
(i) Chandigarh-Kiratpur stretch: The Chandigarh-Kurali section is of 28.6 km length. Out of this, the stretch from km 0.0 to km 11.4 is four/six laned. Four laning from km 11.4 to 15.4 has been sanctioned for Rs.13.51 crore on 31.03.2008 by Ministry. Four laning of the remaining section from km 15.4 to 28.6 is to be taken up under National Highways Development Project (NHDP) Phase – III. The 4 – laning of Kurali-Kiratpur section has been awarded in June 2007 on BOT basis and the work is likely to be completed by June 2010.
(ii) Jalandhar-Amritsar stretch : The Detailed Project Report (DPR) to take up the work of four- laning on Build, Operate and Transfer (BOT) toll basis for Jalandhar-Dhilwan section has been updated by the consultant. The bidding process shall be started after Public Private Partnership Appraisal Committee (PPPAC) clearance. The four – laning of Dhilwan to Verka Chowk, Amritsar section has been started in May 2006 and the work is targeted to be completed by November 2008.
(iii) Amritsar-Pathankot Stretch : The Detailed Project Report (DPR) preparation for four laning of this stretch is in advance stage of completion. The bidding process shall be started after Public Private Partnership Appraisal Committee (PPPAC) clearance.
This information was given by the Minister of State for Shipping, Road Transport and Highways, Shri K.H. Muniyappa in a written reply in the Lok Sabha today.
Source: pib.nic.in
PROPOSAL FOR SETTING UP NATIONAL ROAD SAFETY AND TRAFFIC MANAGEMENT BOARD IS IN FINAL STAGES OF APPROVAL
April 7, 2008
THIRU BAALU ADDRESSES CONSULTATIVE COMMITTEE MEETING
The Union Minister of Shipping, Road Transport and Highways Thiru T.R. Baalu has said that the proposal for setting up of the National Road Safety and Traffic Management Board, as recommended by the Committee on Road Safety and Traffic Management, is in the final stages of approval. Similar Boards would be set up in the States also. Thiru Baalu was addressing the Seventeenth Meeting of the Consultative Committee of Members of Parliament attached to his Ministry here today.
Thiru Baalu also informed the Members that the Department of Road Transport and Highways is also contemplating constitution of a Committee of Experts to suggest a comprehensive scheme to improve the public transport system. The proposed scheme would stipulate certain reform measures to be undertaken by the States to be eligible for seeking financial assistance from the Central Government.
The Minister further informed that a ‘Working Group’ has been constituted by the Government to determine the technology for Advanced Traffic Management System, Advanced Travel or Information System and Electronic Toll collection. He said that a System is proposed to be installed for automatic traffic counting and classification to have better assessment of traffic moving on National highways. He said that these steps are being taken as part of Government’s efforts to give more emphasis on the modernisation of the toll collection system for which introduction of Intelligent Transport System (ITS) is proposed to be gradually introduced.
Thiru Baalu said that a proposal has recently been approved for creation of State and National Registers of driving licenses and registration certificates envisaging inter-linking of all Regional Transport Offices. This would enable creation of authentic database for road transport sector, ensuring transparency in the process of registration of motor vehicles and issuance of driving licenses at a total cost of Rs. 148 crore. The project period is two years. It would check issuance of fake driving licenses / registration certificates and lead to better enforcement of the provisions of the Motor Vehicles Act / Rules, he added.
The Minister also informed that to formulate a scheme for trauma care facilities across the country in general and along the National Highways in particular, his Ministry has been working closely with the Ministry of Health & Family Welfare to work out a -2- combined plan of action. For this purpose, Thiru Baalu informed that the Ministry of Health and Family Welfare has introduced a scheme for setting up of an integrated network of Trauma Centres along the GQ, North-South and East-West Corridors of the National Highways by upgrading the trauma care facilities in 140 identified State Government Hospitals at a total cost of Rs.732.75 crore during the Eleventh Five Year Plan period. Our Ministry has to supply 140 ambulances and NHAI has to provide 50 Ambulances with advanced life support equipment to identified hospitals.
Giving an account of the progress made on the National Highway Development Programme (NHDP), Thiru Baalu observed that upto February 2008, out of the 5,846 kms under the Golden Quadrilateral (GQ) Project, 4/6 laning of about 5,650 kms has been completed and works are in progress in the remaining 196 kms length. Out of about 7,300 kms length under the North-South and East-West Corridors, 4/6 laning was completed in 1,962 kms and works were under implementation in about 4,359 kms. Under NHDP Phase-III, out of 12,109 kms length, 4-laning has been completed in 330 kms and works are in progress in about 1,745 kms and under NHDP Phase-V, out of 6,500 kms length, 6-laning was in progress in about 1,030 kms.
So far 86 projects valued at Rs.29,576.94 crore have been awarded on BOT (Toll) basis. Out of these, 34 projects have been completed and 52 projects are in progress. Also, so far 25 projects valued at Rs. 9,411.88 crore have been awarded on BOT (Annuity) basis; out of which, 8 projects have been completed and 17 projects are in progress, the Minister informed.
The Members of Parliament who participated in the meeting are: S/Shri M.R. Reddy, S. Ajaya Kumar, L.R. Patil, Hari Kewal Prasad, M.L. Mandal, Tiruchi Siva and Ms. Mabel Rebello.
Source: pib.nic.in
SA’s Intertoll barred from NH projects
March 27, 2008
NEW DELHI: After Chinese, Malaysian and Korean firms, the National Highways Authority of India (NHAI) has blacklisted South Africa’s infrastructure firm Intertoll for undertaking road sector projects in the country. Intertoll-led joint venture Intertoll-ICS-Cessons O&M, which had bagged the contract to operate and manage Gurgaon-Jaipur stretch (206 km), has been barred from carrying out any highway project in the country for the next 10 years. “The company has failed to comply with the obligation. It was also found that there was leakage in toll collection. After shooting off showcause notices five times to the firm we have now barred them for the next 10 years for undertaking any project directly or indirectly,” a government official told ET. Last year, the government had put nine firms including Lanco Construction and Essar group in the non-performers’ list. Foreign contractors in the list included Korea’s You-One Engineering Construction, Saudi Arabia’s Sticco, China Coal Construction Group Corporation and Moscow-based Centrodostroy. Four Malaysian companies — UEM Builders, Dolomite Industries, Pati SDN Bhd, and Bhumihighway — were also in the list of non-performers. All highway contractors were blacklisted on account of delay in completing highway projects and poor performance. The dispute between joint venture partners also lead to delay in the projects.“Before we bar any contract we give multiple chances to perform. In case of Intertoll we gave them three years’ time to comply with the contractual obligation,” the official said. Intertoll got the Rs 169-crore contract through competitive bidding to operate, manage and collect toll on the Gurgaon-Jaipur highway for eight years. Foreign infrastructure companies are, however, betting big on the country’s road sector. Recently, these firms won three highway projects out of five offered by NHAI under national highways development project (NHDP)-V. All the three companies — Emirate Trading Agency, Isolux Corsan Group and IJM Corp — which bagged various projects roped in an Indian firm. Source: http://economictimes.indiatimes.com
Plan to upgrade 19 State highways to NHs pending with Centre
March 18, 2008
Hyderabad, March 18:The proposal to convert 19 State highways into National Highways for a length of 4,832.7 km is pending with the Ministry of State Road Transport and Highways (MoSRTH).“We are waiting for their approval,” Roads and Buildings Minister T Jeevan Reddy informed A Uma Madhava Reddy (TDP) and others during the Question Hour in the Assembly on Monday.The minister said that seven roads for periodical renewal works of the length of 68.84 km at a cost of Rs 16.85 crore have been taken up and completed with the funds provided by MoSRTH. Extensive repair works to the badly damaged National Highways have also been taken up to ensure free flow of traffic.The widening of Hyderabad-Vijayawada section of National Highway-9 was being taken up by National Highways Authority of India on BOT basis and the prequalification bids have been invited, the minister said.To another question by P Rajanna Dora, the minister said that Kottaki bridge across Votti Gadda river in Vizianagaram district was in bad shape and a new bridge would be constructed at a cost of Rs 5 crore.Agriculture Minister N Raghuveera Reddy informed K Ramulu (Janata Party) that Chief Minister Y S Rajasekhara Reddy would write a letter to Prime Minister seeking Padma awards to best farmers. He said that awards to the best farmers would be given at mandal levels by the State Government. Source: http://www.siasat.com
Annuity model for Bihar, Jharkhand BOT projects
March 18, 2008
NHAI has not been able to award any project on build-operate-transfer basis via tolling in the states in last two years
New Delhi: Desperate to get the roads programme off the ground in Bihar and Jharkhand, where the private sector is declining all offers—including on lucrative stretches—in view of the challenge from Leftist extremist groups, the Centre is offering investors guaranteed payments instead of recovering their investment by collecting toll revenues. A senior official of the National Highways Authority of India (NHAI), the regulator for highways, who did not wish to be identified, said, “The reason for this (investor disinterest) is partly law and order situation in these states, and Naxalism.” As a result, NHAI has not been able to award a single build-operate-transfer (BOT) highway project through tolling in these states in the last two years. In such highway projects, the company awarded the contract for constructing a stretch of highway collects toll from those using the highway.
Law and order, and Naxalism scare away bidders, who recover their investment from highway tolls
To woo investors towards these highway stretches, NHAI is now planning to recast these BOT projects on an annuity basis, wherein contractors who are awarded projects would be paid a guaranteed amount in instalments. The authority had carved out around 11 highway sections in Bihar for awarding under the BOT mode in 2006 under phase III of the National Highway Development Programme. NHAI first put up its most lucrative stretch, Patna–Muzaffarpur, for bidding in early 2006, but it received no response. “We then tried putting up another stretch for bidding as well, but even then the companies did not show any interest,” said the NHAI official. The authority has faced a similar problem in Jharkhand, where it did not receive any bids for a couple of tolled road projects. The lack of interest in tolling projects in Bihar and Jharkhand is happening at a time when NHAI has made it a policy to gravitate towards BOT projects in order to reduce the government’s investment in the highway sector. Another official in NHAI, who also did not wish to be identified, confirmed that the highways regulator now planned to redraft the proposal for these projects under annuity terms. Members of Parliament from the two states said concerns over viability of the projects apart, private players were hesitant to take up contracts in these areas because they feared for the security of their staff. Bhubaneswar Prasad Mehta, a Lok Sabha member of the Communist Party of India from Hazaribagh in Jharkhand, said even as some tenders were floated last year, there was little response from the private agencies. “Infrastructure development cannot happen in a vacuum,” he said. “Why should anyone risk his life in an area where there is no rule of law and little security? We are planning to raise this issue yet again in our party’s three-day state conference in Ranchi, which begins on 15 March.” However, Nikhil Kumar, a former special secretary for internal security in the Union ministry of home affairs, and a Lok Sabha member of the Congress party from Aurangabad in Bihar, said the situation was somewhat better in his constituency. “I can say for my constituency that though the quality of work remains a matter of concern, wherever we have managed to provide sufficient security to the contractors, with the help of the state government, there has been some progress,” said Kumar. “If the political representatives from these two states, and other areas affected by Naxalism keep pursuing the matter with the state governments and the private executing agencies, we can get the work done. In my constituency alone, about 25 link roads will be constructed under the Pradhan Mantri Gram Sadak Yojana (Prime Minister’s Village Road Programme) and work is set to begin. Earlier, between 2004 and 2007, seven other roads were completed in my constituency,” he added. Ram Deo Bhandary, a Rajya Sabha member of the Rashtriya Janata Dal from Bihar, said it was quite clear that even a few high-profile incidents of violent crime could deter developmental activities.
DF govt to spend Rs 3000 cr on road to power
March 3, 2008
Though its four-year rule in Maharashtra is yet to bring a visible change in the state, the Democratic Front (DF) government now wishes to make amends during its final year in office.
For the 2008-09 fiscal, the state will witness large-scale road construction works, senior officials of the Maharashtra State Road Development Corporation (MSRDC) and Public Works Department (PWD) told ET. The two agencies, which have been keeping a low-profile during the DF rule, compared to the 1995-1999 Shiv Sena-BJP government’s period, want to make up for the lost time. “We will have many more projects to showcase before the people,” Maharashtra chief minister Vilasrao Deshmukh had said earlier.
Road works amounting to more than Rs 3,000 crore have been initiated by these two agencies across the state. All projects are being undertaken on build, operate and transfer (BOT) basis and the state agencies are collaborating with the National Highway Authority of India (NHAI). Such is the project’s volume that the PWD, MSRDC and NHAI would upgrade around 900 km of roads across Maharashtra.
“Most of the roads under construction would be completed in a year or so. We are following a strategy of aggressive development in the road sector, which is one of the main drivers of socio-economic growth. Roads not only connect but also bring investment,” PWD secretary DB Deshpande told ET.
The state is using the Rs 2,000-crore grant sanctioned by the Union government to upgrade the corridors of national highways, which pass through Maharashtra. This allocation has to be used in the 2008-2009 fiscal. The work includes six-laning of the 90-km corridor between Dahisar-Talasari on Mumbai-Ahmedabad National Highway, the 275-km corridor between Satara-Karad-Kagal, which leads to Bangalore, the 86-km stretch between Igatpuri and Pimpalgaon and construction of an elevated 5.5 km long corridor bypassing the Nashik city.
“Maharashtra has always been regarded as the leading state as far as quality of road is concerned. But good roads have utility beyond the obvious connectivity point of view. The World Bank has estimated that an investment of Rs 20 lakh in road works creates one perpetual job.
We are looking at employment generation and economic potential of roads, which would be give an edge to Maharashtra in these industrially competitive times,” an MSRDC official said. Lot of action is also visible on the state highways. The PWD has got Cabinet approval for the Rs 800-crore four-laning of Shirur-Nagar-Pune-Aurangabad state highway, which is 300-km long. “Work has started on this project and should be completed by May 2009,” Mr Deshpande added.
Source: economictimes.indiatimes.com
Madhucon to transfer BOT projects to arm
February 22, 2008
Hyderabad: Madhucon Projects Ltd is planning to transfer its major infrastructure projects to Madhucon Infra Ltd, which shall be a holding company for its build operate and transfer (BOT) toll roads, power projects and coal mines.
The Hyderabad-based company is proposing to transfer its BOT toll road projects and other investments in infrastructure, power and coal mine businesses to Madhucon Infra Ltd and would be seeking the approval of shareholders for the transfer by way of postal ballot, according to a release.
The company to segregate the engineering, procurement had necessitated the transfer process due to a decision and consulting (EPC) business and the investments in BOT projects as the net worth and capital required for these would be substantial. The result of the postal ballot would be announced on March 25, the release added.
Source: sify.com
Reliance Energy is top bidder for Mumbai trans-harbour link project
February 20, 2008
A consortium led by Anil Ambani group company Reliance Energy Ltd (REL) has emerged top bidder for the Rs6,000 crore Mumbai trans-harbour link project.Maharashtra State Road Development Corporation (MSRDC) today opened financial bids for the 25-km six-lane project. However, no confirmation could be obtained from either MSRDC or REL.
Mukesh Ambani-led Reliance Industries group was also in the race for the project to build a trans-habour link between Sewri in Mumbai and Nava-Sheva across the creek in Navi Mumbai.
Sources said the REL-Hyundai combine quoted a lower concession period for the build-operate-transfer (BOT) project of nine years and 11 months as against 75 years quoted by the Mukesh Ambani-controlled Sea King Infrastructure.
Phase-I of the project will comprise a six-lane dual carriageway linking Nhava to Sewri and Phase-II, which is expected to be added in 2015 -18, will consist of a double track rail link that will run parallel to the road link on the north side.
The Rs6,000 crore project is slated for completion in five years. The REL-led consortium can charge Rs250 per heavy vehicle and Rs120 for cars and light commercial vehicles as toll charges.
Source: domain-b.com
Gayatri Projects to hive off invesments in BOT road projects
February 19, 2008
Gayatri Projects is planning to hive off investments in BOT road projects to its subsidiary company with an intention to dilute a part to strategic investors to raise funds for further investment into BOT projects.
A meeting of the board of directors of the company will be held on Feb. 26, 2008, to consider the issue of convertible equity warrants to promoters in accordance with the provisions of SEBI Guidelines, 2000 and allotment of equity shares to FCCB holders upon conversion.
The board will also consider incorporation of new objects clauses in the memorandum of association.
Shares of the company gained Rs 8.4, or 1.62%, to settle at Rs 527.75. The total volume of shares traded was 13,891 at the BSE. (Tuesday)
Source: myiris.com
Punjab farmers bandh peaceful
February 19, 2008
The day-long bandh call given by around 17 pro-kisan organisations seeking waiving off debt and opposing privatisation of state electricity board passed of peacefully in Punjab.
Several farmers’ organisations are protesting the Government’s proposed move to privatise the state electricty board, put up toll plazas under the Build Operate and Transfer (BOT) schemes and sale of public property to generate revenue and demanding waving off Rs 26000 crore debt on state peasantry.
To lodge protest, farmers owing allegiance to Kirti Kisan Union, Bharti Kisan Union, Kisan Sangarsh Committee, Bharti Kisan Committee, Punjab Nirman Sabha, Naujwan Bharat Sabha, Paendu Mazdoor Union and Kranti Kisan union among others blocked vehicular traffic at several places on the national and state highways for about two hours, officials said here.
However, during the bandh call no untoward incident was reported from any part of the state, they said.
Activists of several kisan organisations staged dharnas in the middle of roads at several places across the state, putting commuters to lot of inconvenience.
However, the bandh failed to evoke any response in the cities as all commercial establishments remained opened throughout the day.
At several places, the traffic was diverted in advance by the authorities.
Reports of traffic blockades have been received from Kapurthala, Jalanndhar, Phagwara, Muktsar, Ferozepur, Bathinda, Moga and Faridkot.
Source: hindu.com
