Annuity model for Bihar, Jharkhand BOT projects

March 18, 2008

NHAI has not been able to award any project on build-operate-transfer basis via tolling in the states in last two years

New Delhi: Desperate to get the roads programme off the ground in Bihar and Jharkhand, where the private sector is declining all offers—including on lucrative stretches—in view of the challenge from Leftist extremist groups, the Centre is offering investors guaranteed payments instead of recovering their investment by collecting toll revenues.

A senior official of the National Highways Authority of India (NHAI), the regulator for highways, who did not wish to be identified, said, “The reason for this (investor disinterest) is partly law and order situation in these states, and Naxalism.”

As a result, NHAI has not been able to award a single build-operate-transfer (BOT) highway project through tolling in these states in the last two years. In such highway projects, the company awarded the contract for constructing a stretch of highway collects toll from those using the highway.

 

Law and order, and Naxalism scare away bidders, who recover their investment from highway tolls

 

Prime Minister Manmohan Singh recently said that Naxalites, Leftist extremists, posed the single biggest internal security challenge to the country. As many as 13 out of 28 states in the country are classified as Naxalite-affected.

To woo investors towards these highway stretches, NHAI is now planning to recast these BOT projects on an annuity basis, wherein contractors who are awarded projects would be paid a guaranteed amount in instalments.

The authority had carved out around 11 highway sections in Bihar for awarding under the BOT mode in 2006 under phase III of the National Highway Development Programme.

NHAI first put up its most lucrative stretch, Patna–Muzaffarpur, for bidding in early 2006, but it received no response. “We then tried putting up another stretch for bidding as well, but even then the companies did not show any interest,” said the NHAI official.

The authority has faced a similar problem in Jharkhand, where it did not receive any bids for a couple of tolled road projects.

The lack of interest in tolling projects in Bihar and Jharkhand is happening at a time when NHAI has made it a policy to gravitate towards BOT projects in order to reduce the government’s investment in the highway sector.

Another official in NHAI, who also did not wish to be identified, confirmed that the highways regulator now planned to redraft the proposal for these projects under annuity terms.

Members of Parliament from the two states said concerns over viability of the projects apart, private players were hesitant to take up contracts in these areas because they feared for the security of their staff.

Bhubaneswar Prasad Mehta, a Lok Sabha member of the Communist Party of India from Hazaribagh in Jharkhand, said even as some tenders were floated last year, there was little response from the private agencies. “Infrastructure development cannot happen in a vacuum,” he said. “Why should anyone risk his life in an area where there is no rule of law and little security? We are planning to raise this issue yet again in our party’s three-day state conference in Ranchi, which begins on 15 March.”

However, Nikhil Kumar, a former special secretary for internal security in the Union ministry of home affairs, and a Lok Sabha member of the Congress party from Aurangabad in Bihar, said the situation was somewhat better in his constituency.

“I can say for my constituency that though the quality of work remains a matter of concern, wherever we have managed to provide sufficient security to the contractors, with the help of the state government, there has been some progress,” said Kumar. “If the political representatives from these two states, and other areas affected by Naxalism keep pursuing the matter with the state governments and the private executing agencies, we can get the work done. In my constituency alone, about 25 link roads will be constructed under the Pradhan Mantri Gram Sadak Yojana (Prime Minister’s Village Road Programme) and work is set to begin. Earlier, between 2004 and 2007, seven other roads were completed in my constituency,” he added.

Ram Deo Bhandary, a Rajya Sabha member of the Rashtriya Janata Dal from Bihar, said it was quite clear that even a few high-profile incidents of violent crime could deter developmental activities.

“There haven’t been too many incidents of late, but, of course, law and order remains an area of concern. If contractors are not coming forward to take up work, it is quite clear that the state has not been able to instil confidence in them,” Bhandary said. Source: http://www.livemint.com

NHAI likely to issue contracts for 10,000km of highways soon

March 16, 2008

These contracts will be a part of phase III and phase V of the government’s highway project New Delhi: The United Progressive Alliance government wants to award, in the next few months, contracts to build up to 10,000km of national highways, equal to almost 70% the 14,500km of national highways on which similar contracts have been issued since 2000.Long Road Ahead (Graphic)The decision to award the contracts, worth at least Rs70,000 crore, comes with the general election likely to be held either late this year or early in 2009, although an official at the agency that regulates the highways sector in India claimed that this was because procedural issues related to the contracts had now been “ironed out”.The official at the National Highways Authority of India, or NHAI, added that since 2000, when the country’s National Highways Development Programme or NHDP was launched, the regulator had awarded contracts for the construction of 14,500km of highways worth around Rs80,000 crore and that work on 8,500km had been completed.The contracts that will be issued are part of phase III and phase V of NHDP and involve upgrading existing national highways into four-lane and six-lane ones. Five of the seven phases of NHDP involve upgrading existing highways.The stretches will first be offered to private companies to be developed under the ‘build-operate-transfer’ model where the companies will build the highways, operate them and collect toll for a certain period of time, and transfer them to the government at the end of a certain period of time called the concession period. In case this fails to draw bids, the projects will be offered on the ‘engineering-procurement-construction’ method, where private companies build the roads for a stipulated fee but will not have any stake in the project.“Detailed project reports are being created for these stretches and they are expected to be awarded in the next few months,” said a senior government official, who did not wish to be identified. “There was a lull in award of projects because the policy was being ironed out. But now that things are falling into place, you will see more and more projects on offer,” the official added.For almost a year, NHAI has gone slow in awarding projects.“Till now we were waiting for ironing out procedural issues such as preparation of the new model concession agreement and setting up a two-stage bidding process. Those matters have been taken care of now. And now the only serious impediment in the way of awarding these contracts is clearing of the toll policy,” said an NHAI official.The toll policy is to be cleared by the law ministry and this could take a couple of months, the official added.Analysts however said that while the agency was capable of awarding 8,000km of construction a year, exactly how much would get done depends on a number of factors including a legal challenge to the government’s bid process.The National Highways Builders Federation, an industry body, filed a suit in January against guidelines issued by the finance ministry and ratified by the Prime Minister’s committee on infrastructure that favour bidders who have executed large projects. The norms, reported by Mint on 28 December, cap the number of bidders at six, with some individual exceptions.“There are three factors that could affect the process (of awarding contracts),” said Kuljit Singh, a partner with the transaction advisory services practice of audit and consulting firm Ernst and Young Pvt. Ltd.“Technical detailed project reports usually take a while to prepare. Also, things generally slow down a little in an election year. Also, depending on what the court finds (in the case where the National Highways Builders Federation has challenged NHAI’s bidding norms), the process could be affected,” he added.Source: http://www.livemint.com 

Mega six-lane projects in offing

March 10, 2008

With access-controlled expressways attracting massive investments, the Ministry of Road Transport and Highways has decided to conduct the feasibility study for more such expressways.


  Construction companies eyeing the access controlled, six-lane expressway projects of National Highways Authority of India (NHAI) are likely to get investment opportunities for at least four such projects spread over 495 km over the next few months.They are Chandikhol-Jagatpur-Bhubaneswar (70 kilometre length, estimated cost Rs 761 crore), Delhi-Hapur (47 km, Rs 474 crore), the 198-km stretch of Vijayawada-Elluru-Rajamundri (Rs 1,602 crore) and the 180-km stretch on Delhi-Agra highway (Rs 1,918 crore). The feasibility reports for these projects are already completed and the work is likely to be awarded in about six months, said NHAI officials.Toll collection  These projects are for widening the current four-lane highways into six lanes and operating them for certain durations.Companies would have to bid competitively for these projects on a revenue-sharing basis. Thus companies would have to bid on the extent of toll revenue that they are ready to share with the Government if they are allowed to operate the roads.Since these highways are already four-lane stretches, the road operators can start toll collection even during the project construction phase from an ‘appointed date’ (within six months of winning the project), mutually decided by NHAI and the road operator. The toll revenues will be routed to an escrow account.Recently, the NHAI awarded four such mega projects of 882 km length, which are likely to cost an estimated Rs 10,912 crore.From the NHAI perspective, these projects have emerged as money-spinners, with companies willing to foot the entire construction cost and part with two per cent to 48.06 per cent of their revenues in the initial leg of the project.At the end of the concession period, which is about 12 to 15 years duration, the winning firms have agreed to part with 12 per cent to 59 per cent share of toll revenues.More studies  The feasibility reports for another ten projects of similar nature are under preparation. They are: Kishangarh-Udaipur stretch (315 km, Rs 2,205 crore), Udaipur-Ahmedabad (235 km, Rs 1,645 crore), Varanasi-Aurangabad (190 km, Rs 1,330 crore), Nellore-Chilkaluripet (184 km, Rs 1,288 crore), Krishnagiri-Walajapet (148 km, Rs 1,036 crore), Pune-Satara (145 km, Rs 1,015 crore), Ludhiana-Chandigarh (85 km, Rs 595 crore), Belgaum-Dharwad (80 km, Rs 560 crore), Samakhiali-Gandhidham (56 km, Rs 392 crore), Indore-Dewas (55 km, Rs 385 crore).With access controlled expressways attracting massive investments, the Ministry of Road Transport and Highways has decided to conduct the feasibility study for four such expressways between Delhi-Meerut, Chennai-Bangalore, Vadodara-Mumbai and Dhanbad-Kolkata. This was decided by the Road Ministry officials at a meeting with State Government authorities recently.Source: http://www.thehindubusinessline.com

GPIL announces IPO of 1.65 crore equity shares

March 7, 2008

CHENNAI: With an aim to fund some of its major projects in India, Gammon Infrastructure Projects Limited (GPIL) on Friday announced an initial public offering of 1.65 crore equity shares of par value Rs 10 each for a cash price to be determined through a 100 per cent book-building process (Issue). The price band has been fixed between Rs 167 and Rs 200 pewr equity share. Pervez Umrigar, Managing Director, GPIL, told reporters here today that the Issue’s proceeds would be utilised in the design, construction and maintenance of projects including the four-laning of the 99.5 km of Vadape-Gonde section between Mumbai and Nasik on NH-3, being developed and maintained by the special purpose vehicle (SPV), the Mumbai Nasik Expressway Limted (MNEL). ”We currently have 14 infrastructure projects, including the Vishakaptanam port project in Andhra Pradesh and Mattanchery bridge project in Kerala among others in the operation phase, with respective special purpose vehicles (SPVs) in place to develop and maintain them,” Umrigar said. The Rangit-II hydroelectric power project on River Nimbi in Sikkim, and the MNEL among others were in the development phase, he added. According to a company release, the Issue comprises a net issue of 1.49 crore equity shares to the public (Net Issue) and a reservation of 16.55 lakh equity shares for employees. While at least 60 percent of the Net Issue will be allocated on a proporationate basis to Qualified Institutional Buyers (QIB), at least 10 percent of the same would be available for non-institutional bidders and 30 percent of the Net Issue for retail investors on proportionate basis. The issue opens on March 10 and closes on March 13, 2008. Source: http://economictimes.indiatimes.com

Uttar Pradesh govt plans five more expressways

March 6, 2008

Combined length of 1,400km proposed; roads will be in vicinity of highways being developed by NHAI

The Uttar Pradesh government is planning five more expressways in the state even before it signs the concession agreement for the Rs40,000 crore Ganga Expressway project awarded in January.

And yet again, just as in the case of the Ganga Expressway, the proposed highways are coming up in the vicinity of the highways being developed by the National Highways Authority of India, or NHAI, the roads regulator.

“We will not approach the Centre for any kind of assistance in funding. As in the case of the Ganga Expressway, we will raise resources for these projects by leveraging land,” said an official, who was involved in the planning of the Ganga Expressway project as well, but did not wish to be identified.

Country roads: The Greater Noida expressway. UP had awarded the tender for the Rs40,000 crore Ganga Expressway project, which will connect Greater Noida with Baflia, to Jaypee Infratech Ltd in January. (Madhu Kapparath / Mint)

Country roads: The Greater Noida expressway. UP had awarded the tender for the Rs40,000 crore Ganga Expressway project, which will connect Greater Noida with Baflia, to Jaypee Infratech Ltd in January. (Madhu Kapparath / Mint)

The tender for the Ganga Expressway project, which will connect Greater Noida with Ballia, was awarded to Jaypee Infratech Ltd in January. The concessionaire is expected to be leased around 7,000ha of land for commercial development in order to construct the expressway.

Jaypee had sought land worth Rs293.55 crore for property development along the expressway in order to construct the expressway.

The five proposed expressways will have a combined length of around 1,400km.

“We do not have a clear idea as to how much land will be required to be set aside for these projects, but we will be able to work out those details only after a few months,” the same official said.

The proposed expressways include the Greater Noida-Saharanpur-Dehradun (in partnership with the Uttarakhand state government) stretch apart from Jhansi-Lucknow, Lucknow-Gorakhpur, Agra-Kanpur-Lucknow and Farrukhabad-Kotdwar expressways.

The proposal for these projects is being developed by the state public works department. “First we will seek environmental clearance for these projects and then the proposals will go to the state cabinet for approval,” the official said.

Planning Commission member Anwarul Hoda said that the apex planning organization in the country has not yet been informed about the state’s plans to go in for more expressways. “We have not been told about these projects,” he said.

Earlier, the Planning Commission had held discussions with the UP administration on the Ganga Expressway project in order to see whether the project linked up with existing highway networks in the state. It gave the go-ahead despite the overlap with the highways being developed by NHAI.

“Tolling on these roads will barely pay for operations and management expenses,” said a consultant with a project management company, who did not wish to be quoted. “Remember, these roads are along the same alignment as existing NHAI national highways, which means traffic is going to be shared. So, the capital cost recovery will come from the land component only. If you are in the business of building highways, then why do you need all this land.”

Source: http://www.livemint.com

4-LANING OF DELHI-DEHRADUN NATIONAL HIGHWAY

March 5, 2008

Delhi – Dehradun National Highway has been identified for 4 laning under National Highway Development Project (NHDP) Phase III on Build, Operate & Transfer (BOT) basis. Widening to 4 lane work in Meerut-Muzaffarnagar section is in progress and delayed due to initial problem regarding tree cutting & land acquisition and is targeted to be completed by March, 2009. Widening to 4 lane work in Muzaffarnagar-Haridwar section could not be awarded as only single bid was received and the same was cancelled. For re-bidding of this section, updation of Detailed Project Report (DPR) as per new Model Concession Agreement (MCA) as decided by Public Private Partnership Appraisal Committee (PPPAC) is in progress.The Haridwar-Dehradun section is passing through Rajaji National Park and clearance is to be obtained from the Central Empowered Committee constituted by the Hon’ble Supreme Court of India. After clearance from Central Empowered Committee and PPPAC, bidding process is to be taken up for award of 4 laning work. This information was given by the Minister of State for Shipping, Road Transport and Highways, Shri K.H. Muniyappa in a written reply in the Lok Sabha today.  Source: http://pib.nic.in 

DF govt to spend Rs 3000 cr on road to power

March 3, 2008

Though its four-year rule in Maharashtra is yet to bring a visible change in the state, the Democratic Front (DF) government now wishes to make amends during its final year in office.

For the 2008-09 fiscal, the state will witness large-scale road construction works, senior officials of the Maharashtra State Road Development Corporation (MSRDC) and Public Works Department (PWD) told ET. The two agencies, which have been keeping a low-profile during the DF rule, compared to the 1995-1999 Shiv Sena-BJP government’s period, want to make up for the lost time. “We will have many more projects to showcase before the people,” Maharashtra chief minister Vilasrao Deshmukh had said earlier.

Road works amounting to more than Rs 3,000 crore have been initiated by these two agencies across the state. All projects are being undertaken on build, operate and transfer (BOT) basis and the state agencies are collaborating with the National Highway Authority of India (NHAI). Such is the project’s volume that the PWD, MSRDC and NHAI would upgrade around 900 km of roads across Maharashtra.

“Most of the roads under construction would be completed in a year or so. We are following a strategy of aggressive development in the road sector, which is one of the main drivers of socio-economic growth. Roads not only connect but also bring investment,” PWD secretary DB Deshpande told ET.

The state is using the Rs 2,000-crore grant sanctioned by the Union government to upgrade the corridors of national highways, which pass through Maharashtra. This allocation has to be used in the 2008-2009 fiscal. The work includes six-laning of the 90-km corridor between Dahisar-Talasari on Mumbai-Ahmedabad National Highway, the 275-km corridor between Satara-Karad-Kagal, which leads to Bangalore, the 86-km stretch between Igatpuri and Pimpalgaon and construction of an elevated 5.5 km long corridor bypassing the Nashik city.

“Maharashtra has always been regarded as the leading state as far as quality of road is concerned. But good roads have utility beyond the obvious connectivity point of view. The World Bank has estimated that an investment of Rs 20 lakh in road works creates one perpetual job.

We are looking at employment generation and economic potential of roads, which would be give an edge to Maharashtra in these industrially competitive times,” an MSRDC official said. Lot of action is also visible on the state highways. The PWD has got Cabinet approval for the Rs 800-crore four-laning of Shirur-Nagar-Pune-Aurangabad state highway, which is 300-km long. “Work has started on this project and should be completed by May 2009,” Mr Deshpande added.

Source: economictimes.indiatimes.com

Nine infrastructure firms in customs net

March 3, 2008

Gammon India, Punj Lloyd, Era among those being investigated for diverting tax-exempt equipment for pvt work

The central intelligence unit of Indian customs here has launched a series of cases alleging import duty evasion by nine infrastructure firms, including well-known names in the field such as Punj Lloyd Ltd, Era Constructions (India) Ltd and Gammon India Ltd.

The companies are alleged to have diverted construction machinery, imported without customs duty specifically for projects financed by the United Nations, other international aid organizations and approved by the government, to private projects, thus evading customs duty.

The money involved in the case is not large in itself, but the development is significant since these firms are involved in construction of roads for projects approved by the National Highways Authority of India (NHAI) and aided by the World Bank, Asian Development Bank and the UN.

Under the Customs Act 1962, equipment imported into India for completion of infrastructure projects financed by the UN or an international organization and approved by the government is exempt from customs duty. The firms had imported machinery, such as piling rigs for construction of roads, and had availed the exemption.

Core of the problem

“We have already booked cases against nine firms and have recovered over Rs12 crore against such illegal import of piling rigs,” said R.K. Mahajan, commissioner (general) of customs, Mumbai.

Apart from Punj Lloyd, Era Constructions and Gammon India, the list of companies provided by the customs includes Afcon Infrastructure Ltd, Ircon International Ltd, Meher Foundation and Civil Engineers Pvt. Ltd, Villayati Ram Mittal Pvt. Ltd (New Delhi), Vijay M Mistry Construction Pvt. Ltd and Maytas Infra Pvt. Ltd.

Each piling rig costs around Rs4 crore and attracts close to Rs1 crore import duty.

“We have also seized piling rigs worth Rs8.25 crore,” Mahajan said. According to him, these companies have evaded customs duty of at least Rs20 crore and the amount could be even more as the investigation is not yet complete.

The infrastructure projects are spread across India. For instance, Punj Lloyd, one of the largest engineering and construction firms engaged in infrastructure projects, had imported piling rigs for its two NHAI-approved projects in Assam, but, according to the customs intelligence unit, these rigs were diverted to New Delhi.

“The company had rented out one of the machines to Delhi Metro Rail Corp. Ltd,” claimed a senior officer of customs who did not wish to be named.

However, the firm admitted it has been “summoned by the central intelligence unit, Mumbai customs, seeking certain clarifications/information pertaining to import of hydraulic operated self-propelled piling rig along with accessories,” imported by it under customs duty exemption scheme.

“Unfortunately, by the time such rig, along with its accessories, touched the boundaries of India it was realized that the said rig etc. could not be optimally utilized at the Guwahati to Nalbari Section of NH31 in Assam project due to non- availability of work… Since the machinery so imported was worth crores of rupees and keeping it idle would not only result in decaying and deterioration but also have an adverse financial impact…the company deemed it prudent to deploy the same to some other appropriate site,” the company wrote in its email.

It admitted that the rig was deployed at the DMRC project “which included construction of roads.” Stating that “by utilizing the…rig at the DMRC project we were in a position to keep the same in running condition,” the company said in its email that the rigs would be used at the Assam project “the moment we receive a green signal…from NHAI.”

“We believe we have acted within the intent and framework of the customs notification and the undertaking and there is no violation of any nature whatsoever and your source on information about the tax evasion on our part is unfounded and baseless,” the email went on to say.

The New Delhi-based Era Constructions, now known as Era Infra Engineering Ltd, was awarded two contracts for construction of roads in Chhattisgarh. However, according to the customs, the machinery was allegedly rerouted to other parts of India. “During the investigation, one of the machines was found at the NTPC Ltd’s site in Dadri in Uttar Pradesh. The other was found in Haryana,” Mahajan said.

Era Infra’s vice-president (commercial) Anil Bhasin said the firm had paid customs duty and interest for the equipment, which was shifted to other nationally important projects of government and public sector undertakings. According to him, the company diverted a few equipment that were not required at the assigned projects to other sites. It actually wanted to return these equipment, but could not do so as there was no provision to return such equipment. “The customs duty for such equipment was paid,” insisted Bhasin.

Gammon India, a Mumbai-based construction firm, according to Mahajan, has violated the rules by diverting machinery to another location for private use. However, he declined to disclose the location where the equipment was transferred and said the case was under investigation.

Gammon India, too, denied being involved in customs duty evasion. “There may be a possibility that some construction companies who have imported equipment under such exemptions could have utilized the same for projects other than for which such exemptions are applicable like, real estate, housing projects, shopping malls, etc. To clarify your doubts, Gammon does not undertake real estate/housing projects which could have been a potential misuse as per your concern. In fact, central intelligence unit had enquired about the utilization from all the importers who had imported equipment under the above exemptions,” said Umakant Tiwari, assistant general manager (procurement), Gammon India, in an email response.

Source: livemint.com

A capital cost of capacity

March 3, 2008

Demand is growing faster than anticipated. And there is such dearth of infrastructure that new capacities will be absorbed promptly

Last month, the showpiece urban transportation project, the 28km Delhi-Gurgaon expressway was inaugurated. Another big-ticket project, Bangalore International Airport Ltd, is set to begin operations in March. In the case of the expressway, traffic on the first day was what was projected for 2013. In Bangalore, the passenger traffic will cross 11.3 million—a number initially projected for 2015—by the end of the year. In both cases, capacities for the first year are inadquate.

Clearly, the project planners in both instances got their projections quite wrong. But, if one steps back, a more complex picture emerges. The most obvious fact is that demand is growing faster than anticipated. And there is such dearth of infrastructure that new capacities will be absorbed promptly. In contrast, China seems to be a case of excess capacities.

Another factor being debated is that this is not a simple case of an owner-operator failing to anticipate traffic. Any entrepreneur would see the obvious and plan for it. Instead, it is argued, given the cost of capital, one shouldn’t expect anything different. Our real interest rate—corrected for inflation—is about 7%, probably among the highest in the world. Hence, the entrepreneur’s action would be an error of commission—to minimise project risk.

The other side of the coin is that the pricing of public services is subsidized, largely to ensure that the less well off can avail the benefits. In other words, far more people can afford to consume these services than otherwise. While not making a case for leaving out these segments, there is need to strike a correction.

The reason is simple.

Subsidized consumption, like other political largesse, comes at a fiscal cost. Not only does this push up the cost of capital, it also—since government borrowings inevitably expand money supply—stokes inflationary pressures, hurting the very people that the government set about protecting. In China it is the opposite, where fiscal profligacy subsidizes investment.

Both extremes are unsustainable. Given India’s mixed socio-economic demography, there is a case for revisiting subsidized consumption. A good beginning would be if the political parties arrive at a consensus that ensures bad economics will no longer be passed off as sensitive politics.

A precedent exists. Gujarat, in the early 1990s, had come out with a document detailing an all-party commitment to structural reforms in the state. That no doubt underlines the economic success of the state over the past decade.

Source: livemint.com

Highways rev into the fast track

March 1, 2008

Fasten your seat belt and get ready to zoom on Indian highways. The FM has increased the outlay for the National Highway Development Programme from Rs 10,867 crore in last Budget to Rs 12,966 crore this time. With the surface transport ministry just having finalised new model concessionaire agreements and other policies, it is set to put implementation in the higher gear. ”We have a big implementation plan for next fiscal that includes six or four laning of highways. The progress will be at a very fast pace now as the Budget gives NHDP a big push,” said Brahm Dutt, secretary, ministry of surface transport and roads. Among the ongoing projects that will get a push — finishing the 5,846-km golden quadrilateral linking Delhi-Mumbai-Chennai-Kolkata that’s already 96.48% complete and making progress on the 7,300-km north-south and east-west corridors that are 23.36% ready. The FM laid emphasis on Northeast and said the existing 180 km would go up to 300 km in 2008-09. Source: http://timesofindia.indiatimes.com 

« Previous PageNext Page »