TEXT-Fitch affirms SNBTPL ‘s bank loans at BBB-(ind)

April 19, 2010

April 16 – Fitch Ratings has today affirmed SEW-Navayuga Barwani Tollways Pvt Ltd.’s (SNBTPL) senior long-term project bank loans aggregating INR5,474m at ‘BBB-(ind)’, and subordinated bank loans of INR300m at ‘BB+(ind)’. The Outlook is Stable.

SNBTPL enjoys an 18-year concession from National Highways Authority of India [NHAI.UL] (NHAI, ‘AAA(ind)’/Stable) to design, engineer, build, finance, construct, operate and maintain on a Build, Operate and Transfer (BOT) basis an 82.8km road stretch on the National Highway 3 (NH-3) in the state of Madhya Pradesh. The estimated cost of the project is INR7.9bn, with the scheduled commercial operations date (COD) in May 2011.

The affirmations follow SNBTPL’s reasonable progress over the last year in achieving different project milestones during the critical construction phase. Fitch does note however that the company is slightly behind plans. The entire right of way (ROW) required for the project is reportedly in the company’s possession, with the exception of a three-km stretch of forest land; however, first-stage approvals have been received from the forest department.

As of March 2010, the project has received equity infusions (61.3%), and has been drawing down on term loans – 58% of senior debt and 57% of sub-debt – as per schedule.

The ratings are constrained by the residual completion risk, although a fixed-price construction contract with SEW, whose terms mirror those in the concession, offer protection. Base-case debt service coverage metrics are extremely modest and vulnerable to various deep stress tests Fitch performed. A three-year tail in the concession allows the banks to restructure the loans, if necessary. Some liquidity support is available in the form of a fully-funded debt service reserve account (DSRA), equivalent to three months’ principal and interest payment.

Fitch has factored into its rating the operational track record and financial strengths of the sponsors. This includes the credit enhancement value of their undertaking to finance the cost and time overruns, to replenish the senior and subordinated DSRA and to provide unconditional and irrevocable bank guarantees if event project cash flows are inadequate to create the DSRA. Additionally, SEW has executed a letter of undertaking to the senior to infuse INR100m, after the COD, to augment debt payment capacity and to inject additional funds in case operations and maintenance expenses exceed the base case projections submitted to the banks.

The agency believes that the road has long-term economic potential, and that its locational advantage should have a beneficial impact on tollable traffic. Also, it is situated on the highway that represents the shortest distance between Mumbai and Agra.

SNBTPL is a 74:26 JV between SEW infrastructure Ltd (SEW, ‘AA-(ind)’ / Stable) and Navayuga Engineering Constructions Ltd (NECL). Following inter-se adjustments among the sponsors, SEW has increased its equity stake in the project to 74% from the 51%, resulting in a reduction in NECL’s holding to 26%.

Applicable Criteria available on Fitch’s website at www.fitchratings.com: “Rating Criteria for Infrastructure and Project Finance”, dated September 29, 2009.

Source: in.reuters.com

Share your comments here: