NHAI to relay Aroor stretch on Friday

December 13, 2013

TNN

KOCHI:National Highways Authority of India (NHAI) will relay the damaged stretch between Aroor and Kumbalam on NH66 (old NH47) on Friday.

The authority said that the machines required to carry out road milling works are on the way to Kochi from Andhra Pradesh.

 NHAI project director C T Abraham said: “The plan is to grind the existing tarred surface and remove asphalt. We have to seal the concrete surface below and make it watertight. Later, the stretch will be relayed using bitumen concrete.”

NHAI had closed the Aroor-Kumbalam bridge after its surface developed large potholes that posed a threat to motorists. After inspecting the bridge, experts from IIT Madras had recommended that the entire tarred surface be removed. The bridge was built in 1987 and the authority stated that under present circumstance it was not possible to dismantle it.

Abraham said that the immediate concern of NHAI was to repair the road and make it motorable. The authority stated that though milling works are rarely carried out in the state, the works undertaken in Kochi was a ‘minor task which could be completed in a day’.

The estimated cost for the carrying out the work is around Rs 2.5 lakh. tnn The National Highways Authority of India (NHAI) will relay the damaged stretch on NH66 (old NH 47) between Aroor and Kumbalam on Friday. The authority said that the machine required for carrying out the “road milling works” are on the way to Kochi from Andhra Pradesh.

NHAI project director C T Abraham said, “The plan is to grind the existing tarred surface and remove asphalt. We have to seal the concrete surface below and make it water tight. Later, the stretch will be re-layed using bitumen concrete.”

NHAI had closed the Aroor-Kumbalam bridge after its surface developed large potholes, which posed grave threat to motorists. After inspecting the bridge, experts from IIT Madras had recommended to break up the entire tarred surface. The bridge was built in 1987 and the authority stated that under the present circumstance it was not possible to dismantle it.

Abraham said that the immediate concern of NHAI was to repair the road and make it motorable.

The authority stated that though milling works are rarely carried out in the state, the works undertaken in Kochi was a ‘minor task which could be completed in a day’. The estimated cost for the carrying out the works is around Rs 2.5 lakh.

 

Source-http://articles.timesofindia.indiatimes.com/