Nanjundapuram flyover works likely to be over by this month

July 8, 2014

M. SOUNDARIYA PREETHA

 The road work for the bridge across the railway gate on Nanjundapuram road is yet to be completed. Photo: S. Siva Saravanan

The Hindu The road work for the bridge across the railway gate on
Nanjundapuram road is yet to be completed. Photo: S. Siva Saravanan

The contractor has paid Rs. 17 lakh penalty

Works for a bridge across the railway line on Nanjundapuram road are expected to be completed by the end of this month, according to an official of the State Highways Department.

The official told The Hindu that the bridge works are over, and the road — 150 metres on one side and 90 metres on the other — needs to be completed. The total cost for the road work is Rs. 40 lakh.

The contractor has paid Rs. 17 lakh penalty so far for delay in completing the works. Land acquisition has been completed for the road works.

The project is getting delayed because of financial problems for the contractor. It was expected to be completed in last month.

The cost for the project was fixed in 2009-10 and the contractor is incurring loss now because the costs have gone up. If the works are not completed by the end of this month, the department will look at cancelling the contract, the official said.

The Rs. 12.6-crore project involves construction of 693 metre, two-lane bridge. It includes 337.75 metre road on the Ramanathapuram side and 317.26 metre road on the Podanur side.

Works started more than two years ago and land acquisition was completed in August last year. The works were expected to be completed by December, 2013.

Source-http://www.thehindu.com/