Governmentt, NHAI resolve differences over highway

December 23, 2013

TNN |

 

JAIPUR: Finally, after being at loggerheads for several months on various issues regarding widening of Jaipur-Gurgaon stretch of national highway (NH-8), the state government andNational Highways Authority of India (NHAI) has reached a consensus on two major impediments. NHAI received an estimate for the relocation of two high-tension power (HTP) lines on Wednesday, while the state government handed over the land at Sanjay Van to the authorities.
After dilly-dallying for 20 months, the Jaipur Vidyut Vitran Nigam Limited (JVVNL) has given the total costing for the relocation of two HTP lines from Jaipur bypass. The JVVNL will roughly take two months for processing the tender and another two months for shifting it after which NHAI is expected to start construction in the patch.

NHAI is examining the estimate and clarification submitted by the electricity board and is likely to take final decision on it soon. The issue was pending with the Jaipur discom for past many months leading to a delay in widening the stretch. However, after a team of engineers went to Japan to study the technology for transfer of lines, the JVVNL has agreed to initiate the work.

In another major breakthrough, the state government provided land to the concessionaire for carrying out work at Sanjay Van. Earlier, the government was demanding construction of a boundary wall from the developer in lieu of handing over the forest land, which NHAI rejected. It maintained that a payment of Rs 1.15 crore has already been made to forest department as a part of compensation. After intervention from the officials of NHAI and state government, the issue was finally settled.

“Our efforts are on to remove all hindrances for all the national highway projects in the state including important linkage between Delhi-Jaipur. I am hopeful that most of the issues will be sorted out soon and inconvenience caused to commuters will be reduced to minimum possible extent,” said AK Mishra, chief general manager (technical-NHAI), Rajasthan.

Jaipur: After locking horns for several months on various issues in widening of Jaipur-Gurgaon stretch of national highway (NH -8), the state government and National Highway Authority of India reached a consensus on two major impediments. NHAI has received an estimate for the relocation of two high tension power (HTP) lines on Wednesday while state government has handed over the land at Sanjay Van to the authority.

After dillydallying for 20 months the Jaipur Vidyut Vitran Nigam Limited has given the total costing for the relocation of two HTP line from Jaipur bypass. The JVVNL will roughly take two months for processing the tender and another two months for shifting it after which NHAI is expected to start construction in the patch.

NHAI is examining the estimate and clarification submitted by the electricity board and is likely to take final decision on it soon. The issue was pending with the Jaipur discom for the past many months leading to delay in widening of the stretch. However after a team of engineers went to Japan to study the technology for transfer of lines, the JVVNL has agreed to initiate the work.

In another major break through, the state government provided land to the concessionaire for carrying out work at Sanjay Van. Earlier, the government was demanding construction of a boundary wall from the developer in lieu of handing over the forest land, which NHAI rejected. It maintained that a payment of Rs. 1.15 cr has already been made to forest department as a part of compensation. After intervention from the officials of NHAI and state government issue was finally settled down.

“Our efforts are to remove all hindrances for all the national highway projects in the state including important linkage between Delhi-Jaipur. I am hopeful that most issues will be sorted out soon and inconvenience caused to commuters will be reduced to minimum possible extent” said AK Mishra, chief general manager (Tech), Rajasthan.