STATUS OF WORK ON SELECTED HIGHWAY STRETCHES IN PUNJAB

April 23, 2008

The status of Chandigarh-Kiratpur, Amritsar-Pathankot and Jalandhar –Amritsar stretches are as under:

(i) Chandigarh-Kiratpur stretch: The Chandigarh-Kurali section is of 28.6 km length. Out of this, the stretch from km 0.0 to km 11.4 is four/six laned. Four laning from km 11.4 to 15.4 has been sanctioned for Rs.13.51 crore on 31.03.2008 by Ministry. Four laning of the remaining section from km 15.4 to 28.6 is to be taken up under National Highways Development Project (NHDP) Phase – III. The 4 – laning of Kurali-Kiratpur section has been awarded in June 2007 on BOT basis and the work is likely to be completed by June 2010.

(ii) Jalandhar-Amritsar stretch : The Detailed Project Report (DPR) to take up the work of four- laning on Build, Operate and Transfer (BOT) toll basis for Jalandhar-Dhilwan section has been updated by the consultant. The bidding process shall be started after Public Private Partnership Appraisal Committee (PPPAC) clearance. The four – laning of Dhilwan to Verka Chowk, Amritsar section has been started in May 2006 and the work is targeted to be completed by November 2008.

(iii) Amritsar-Pathankot Stretch : The Detailed Project Report (DPR) preparation for four laning of this stretch is in advance stage of completion. The bidding process shall be started after Public Private Partnership Appraisal Committee (PPPAC) clearance.

This information was given by the Minister of State for Shipping, Road Transport and Highways, Shri K.H. Muniyappa in a written reply in the Lok Sabha today.

Source: pib.nic.in